Boiler tube banks for the Chuquicamata smelter

Fabrication at the Concón shop of boiler tube banks for the convection section of the Chuquicamata smelter boiler, from the receipt and inspection of the A192 tubes to the escorted dispatch of boiler bank No. 6.

The project began with the receipt of the lot of A192 boiler tubes and the inlet and outlet headers for each bank, shipped from Argentina. The material was stored and inspected by the quality team against the purchase order and the technical specifications before being released for fabrication.

At the shop, following the fabrication drawings, the serpentine coils that make up each bank were cut, sized, laid out on jigs and welded. Boiler bank No. 6, weighing about 13 tonnes and with more than 1,000 welded joints, passed its quality certification and was lifted with an 80-tonne crane onto a lowboy truck for escorted transport to the smelter, where it replaces the existing bank and extends the service life of the equipment.

13t
Weight of boiler bank No. 6
80t
Capacity of the lifting crane
+1,000
Welded joints
6 to 7 months
Fabrication, certification and dispatch

Scope delivered.

What LTF delivered on this project, item by item. The photo follows each item as you scroll.

  1. 01

    Receipt, storage and quality inspection of A192 tubes and headers

    The A192 tubes and the inlet and outlet headers for each bank arrived from Argentina. The quality team inspected them against the purchase order and the technical specifications before releasing them for fabrication.
    Inspection of the tubes in storage
  2. 02

    Cutting, sizing and jig layout according to drawings

    The tubes were cut, sized and laid out on jigs at the Concón shop, following the fabrication drawings for each bank.
    Drawing review in the technical office
  3. 03

    Welding of the boiler tube serpentine coils

    The serpentine coils that make up each bank were welded at the shop. Boiler bank No. 6 has more than 1,000 welded joints.
    Welding in the shop booth
  4. 04

    Quality certification of the fabricated bank

    Before leaving the shop, boiler bank No. 6, weighing about 13 tonnes, passed its quality certification.
    Ultrasonic measurement on an A192 tube
  5. 05

    Lifting, loading and escorted dispatch to the smelter

    An 80-tonne crane lifted boiler bank No. 6 onto a lowboy truck for escorted transport to the smelter, where it replaces the existing one and extends the service life of the equipment.
    Lifting the bank onto the lowboy, drone view

Video record.

Filmed on site. Turn on the sound to watch the full record with audio. English subtitles are shown over the original Spanish captions.

01Receipt and inspection of the A192 tubes01:35
02Dispatch of boiler bank No. 601:17

Project record.

Photos taken on site. Tap any image to see it in full, zoom in and browse all 17 from the project.

Unloading at the shop
02Unloading at the shop
Lot of A192 tubes on the truck
05Lot of A192 tubes on the truck
Unloading the tube lot from the truck
06Unloading the tube lot from the truck
Review of a fabrication drawing
11Review of a fabrication drawing
Securing the load on the truck
13Securing the load on the truck
Crane lift maneuver
15Crane lift maneuver
Securing the bank on the lowboy
16Securing the bank on the lowboy

Chuquicamata smelter, Calama. Fabricated at the LTF shop in Concón.

Site context

The Chuquicamata smelter is Codelco’s largest, with a smelting capacity of 1.4 million tonnes per year around the middle of the last decade, and it runs a flash furnace whose waste heat boiler recovers energy from the process off-gases. Since 2020 the plant recorded an increase in tube rupture failures in that boiler, and in the major maintenance shutdown of November 2022, lasting 135 days, about 50% of its heat exchange surface was replaced, as reported by Diario Financiero.

In that context, a new tube bank, fabricated, certified and dispatched from the Concón shop, is what allows the existing one to be replaced and the service life of the equipment to be extended between shutdowns. The tubes are ASTM A192, the standard for seamless carbon steel boiler tubes for high-pressure service.