Oxygen lines of 16, 20 and 24 inches

Fabrication and installation of 16, 20 and 24 inch oxygen lines for the Chuquicamata smelter, with SSPC-SP5 blasting and painting, installation of flowmeters and pneumatic testing of the system. Workforce of 50.

Oxygen enriches the air that feeds the smelting and converting processes of the smelter. LTF fabricated and installed 16, 20 and 24 inch lines for its distribution, with surface preparation by white metal blasting, grade SSPC-SP5, and painting.

Installation included the system flowmeters and ended with its pneumatic tests. The job was carried out with 50 people, with a telescopic crane for lifting the sections, and was recorded in November 2020.

24"
Largest line diameter
SSPC-SP5
White metal blast cleaning
50
People on the job
Pneumatic test
Of the complete system

Scope delivered.

What LTF delivered on this project, item by item. The photo follows each item as you scroll.

  1. 01

    Fabrication and installation of 16, 20 and 24 inch oxygen lines

    Oxygen enriches the air that feeds the smelting and converting processes of the smelter. These lines distribute it.
    Installing a section on the platform
  2. 02

    Blasting and painting, grade SSPC-SP5

    The surface was prepared by white metal blasting, grade SSPC-SP5, before painting.
    Line in position next to the stairs
  3. 03

    Installation of flowmeters

    The flowmeters measure the flow of oxygen through the system.
    Lifting maneuver next to the building
  4. 04

    Pneumatic tests of the system

    Installation ended with pneumatic tests of the complete system.
  5. 05

    Workforce of 50

    The job had a telescopic crane for lifting the sections and was recorded in November 2020.