Projects delivered with the plant in operation.

Shop fabrication and site installation for top-tier clients, with certified quality and the safety protocols each Division requires.

01 · Project sheets

Codelco smelters, from Chuquicamata to Potrerillos.

Each sheet brings together the scope delivered, the workforce, the technical data, the site context and the photo record of the project.

Codelco, Chuquicamata Division · 2025

Boiler tube banks for the Chuquicamata smelter

Fabrication at the Concón shop of boiler tube banks for the convection section of the Chuquicamata smelter boiler, from the receipt and inspection of the A192 tubes to the escorted dispatch of boiler bank No. 6.

View the project sheet
Codelco, Salvador Division · 2025

Crane maintenance and rail replacement at the Potrerillos smelter

Maintenance of the PH cranes in the smelter building, rail replacement, and fabrication and erection of structures at the Potrerillos smelter of Codelco Salvador, with a workforce of 75.

View the project sheet
Boiler tube serpentine coils fabricated at the LTF shop
Codelco, Chuquicamata Division · 2020 and 2021

Boiler banks, wall panels and boiler maintenance

Fabrication of convection and radiant banks, wall panels and bends for the boilers of the Chuquicamata Division, with their installation, steam drum maintenance, and hydrostatic tests and non-destructive testing of every system. Workforce of 200.

View the project sheet
Copper cooling circuits connected to a stainless steel manifold
Codelco, Chuquicamata Division · 2023

Flash Furnace cooling system

Fabrication and installation of the cooling circuits of the Chuquicamata Flash Furnace, with silver brazing, 316L stainless steel supply manifolds and 6, 8 and 10 inch lines. Workforce of 200 on rotating shifts.

View the project sheet
Copper pouring into the molds of the Chuquicamata casting wheel
Codelco, Chuquicamata Division · 2021 and 2023

Replacement of casting wheels 3 and 4

Complete dismantling and installation of casting wheels 3 and 4 at the Chuquicamata smelter, from the spokes, rollers and racks to the hydraulic system, take-off and weighing scales, with commissioning and calibration. Workforce of 150 on double shifts.

View the project sheet
Ladles in the Flash Furnace building of the Chuquicamata smelter
Codelco, Chuquicamata Division · 2021

Flash Furnace ancillary works contract

Ancillary works contract for the Chuquicamata Flash Furnace: ladle enclosures, fugitive gas system piping, copper launders, baghouse filters, electrically actuated valves and installation of the VTI and VTF units. About 250 people on double shifts.

View the project sheet
Towers and structures of the Chuquicamata smelter acid plant
Codelco, Chuquicamata Division · 2021

ZeCor-Z welding and acid plant maintenance

ZeCor-Z welding from 2 to 16 inches, catalyst replacement, repair of FRP equipment, and fabrication and installation of ZeCor and FRP piping at the acid plant of the Chuquicamata smelter. Workforce of 150 on double shifts.

View the project sheet
Inside dryer 6 with the coil sections
Codelco, Chuquicamata Division · 2024

Fabrication and maintenance of dryer 6 coils

Fabrication of five coil sections in super duplex steel for dryer 6 of the Chuquicamata smelter, with their installation, repair of the dryer shell, and replacement of the piping and electrically actuated valves. Workforce of 140 on rotating shifts.

View the project sheet
Work on a line of the Flash Furnace cooling system
Codelco, Chuquicamata Division

Flash Furnace and boiler cooling, 18 inch line

Removal of the old circuits and fabrication and installation of the new cooling piping system for the Flash Furnace and its boiler, with an 18 inch line and about 10,000 diameter inches, supports, painting, booster pumps and hydrostatic testing. Workforce of 250.

View the project sheet
Chuquicamata smelter building seen from a drone
Codelco, Chuquicamata Division · 2021

Crane rail replacement at the Chuquicamata smelter

Replacement of the crane rails in the Chuquicamata smelter building: electrical and mechanical lockout of the cranes, cutting and removal of the existing rails, and installation of the new ones with bracket welding. Workforce of 90.

View the project sheet
Oxygen lines installed at height at the Chuquicamata smelter
Codelco, Chuquicamata Division · 2020

Oxygen lines of 16, 20 and 24 inches

Fabrication and installation of 16, 20 and 24 inch oxygen lines for the Chuquicamata smelter, with SSPC-SP5 blasting and painting, installation of flowmeters and pneumatic testing of the system. Workforce of 50.

View the project sheet
Two LTF workers inside the precipitator at the Ministro Hales Division, among the electrodes
Codelco, Chuquicamata and Ministro Hales Divisions

Electrostatic precipitator maintenance

Maintenance of electrostatic precipitators at the Chuquicamata and Ministro Hales divisions: cleaning and replacement of fields and electrodes, scraper conveyors, electrical systems and all internals, through to commissioning. A workforce of 170 people on double shifts.

View the project sheet

Site record

Photo record of the twelve published projects
Acid plant, Chuquicamata · Front of the plant during maintenance
Ministro Hales precipitator · Cutting with an angle grinder
Chuquicamata smelter · Supervision on the casting wheel during installation
Potrerillos smelter · LTF workers on the platform above the building
Flash Furnace, Chuquicamata · Circuits connected to the manifold
Chuquicamata smelter · Smelter building and crane runway beams
Chuquicamata boiler · Welding of tube panels
Concón shop · Lifting the boiler bank onto the lowboy, drone view
Chuquicamata smelter · Oxygen line section on the structure
Dryer 6, Chuquicamata · Installing coils at the dryer mouth
Flash Furnace, Chuquicamata · Ladle in the furnace building
01 / 11 · Acid plant, Chuquicamata · Front of the plant during maintenance