ZeCor-Z welding and acid plant maintenance

ZeCor-Z welding from 2 to 16 inches, catalyst replacement, repair of FRP equipment, and fabrication and installation of ZeCor and FRP piping at the acid plant of the Chuquicamata smelter. Workforce of 150 on double shifts.

The acid plant converts the sulfur dioxide in the smelter off-gases into sulfuric acid. Its lines handle concentrated acid and are built with special materials: ZeCor, an alloy developed to resist sulfuric acid corrosion, and FRP, fiberglass-reinforced plastic. LTF performed ZeCor-Z welding in diameters of 2, 4, 6, 8, 10, 12, 14 and 16 inches, and fabricated and installed ZeCor and FRP piping.

Maintenance included catalyst replacement, with the catalyst removed and replaced in bulk bags like those seen in the record, and repair of FRP equipment. The project was carried out with 150 people on a double-shift system.

8
Diameters welded in ZeCor-Z, from 2 to 16 inches
150
People on double shifts
Catalyst
Removal and replacement
FRP
Repair of equipment and piping

Scope delivered.

What LTF delivered on this project, item by item. The photo follows each item as you scroll.

  1. 01

    ZeCor-Z welding in 2, 4, 6, 8, 10, 12, 14 and 16 inch diameters

    ZeCor is an alloy developed to resist corrosion from the concentrated sulfuric acid the plant’s lines handle. LTF welded ZeCor-Z in eight diameters.
    Removed catalyst in bulk bags
  2. 02

    Catalyst replacement

    The catalyst was removed and replaced in bulk bags, like those seen in the project record.
    Conical bottom of a plant vessel
  3. 03

    Repair of FRP equipment

    FRP, fiberglass-reinforced plastic, is one of the special materials the plant is built with to handle concentrated acid.
    Installing an FRP line between structures
  4. 04

    Fabrication and installation of ZeCor and FRP piping

    The lines were fabricated and installed in ZeCor and FRP, with sections lifted by crane and installed from scaffolding.
    FRP section being installed on scaffolding
  5. 05

    Workforce of 150 on double shifts

    The maintenance was carried out by 150 people on a double-shift system, with work at the plant by day and by night.
    Bulk bags with catalyst, seen from above

Project record.

Photos taken on site. Tap any image to see it in full, zoom in and browse all 17 from the project.

Plant structures and platforms
04Plant structures and platforms
Conical bottom above the removed catalyst
07Conical bottom above the removed catalyst
Worker in harness at a vessel opening
09Worker in harness at a vessel opening
Crane lift of a section
12Crane lift of a section
Plant platform at night
13Plant platform at night
Platforms and stairs of the acid plant
16Platforms and stairs of the acid plant
Front of the acid plant during maintenance
17Front of the acid plant during maintenance

Acid plant, Chuquicamata smelter.

Site context

Acid plants are the centerpiece of compliance with Supreme Decree No. 28 of 2013, which requires smelters to capture and fix at least 95% of the sulfur entering the process. The captured sulfur leaves the smelter as sulfuric acid, which the mining industry itself uses in its leaching processes.