Flash Furnace and boiler cooling, 18 inch line
Removal of the old circuits and fabrication and installation of the new cooling piping system for the Flash Furnace and its boiler, with an 18 inch line and about 10,000 diameter inches, supports, painting, booster pumps and hydrostatic testing. Workforce of 250.

LTF removed the old piping circuits and fabricated and installed the new cooling system for the flash furnace and its boiler, in various diameters and with an 18 inch line. The job reached about 10,000 diameter inches, the unit used to measure piping welding work: the sum of the diameters of every welded joint.
The job included fabrication and installation of the entire support system, blasting and painting of the circuits, and installation of the booster pumps. Each circuit was delivered with its hydrostatic test. 250 workers took part on a rotating shift system.
Scope delivered.
What LTF delivered on this project, item by item. The photo follows each item as you scroll.
- 01
Removal of the old piping circuits
The old circuits were removed to make way for the new cooling system of the flash furnace and its boiler.
- 02
Fabrication and installation of the piping system in various diameters, about 10,000 diameter inches
Diameter inches measure piping welding work: the sum of the diameters of every welded joint. The system includes an 18 inch line.
- 03
Fabrication and installation of the entire support system
LTF fabricated and installed all the supports that carry the line sections.
- 04
Blasting and painting of all circuits
Blasting prepares the steel surface to receive the paint. It was applied to every circuit.
- 05
Installation of booster pumps
The booster pumps drive the water through the new cooling system.
- 06
Hydrostatic test of each circuit
Each circuit was delivered with its hydrostatic test: the water circuit is what keeps the boiler in service.
- 07
Workforce of 250 on a rotating shift system
Working at this plant requires coordinating every maneuver with operations and with the Division’s shifts.
Project record.
Photos taken on site. Tap any image to see it in full, zoom in and browse all 14 from the project.
Chuquicamata smelter, Calama.
Site context
The Chuquicamata Flash Furnace boiler recovers heat from the process gases, and its water circuit is what keeps it in service. In November 2022 the smelter entered a 135-day major maintenance shutdown centered on that boiler, as reported by Diario Financiero. Working in that plant requires coordinating every maneuver with operations and with the Division’s shifts.
LTF Montajes Industriales · +56 9 9431 6903 · [email protected] · ltfmontajes.cl
Crane rail replacement at the Chuquicamata smelter
Codelco, Chuquicamata Division · Chuquicamata smelter, Calama View the sheet
Project index
12 project sheets for Codelco- 01 Boiler tube banks for the Chuquicamata smelter Chuquicamata smelter 2025
- 02 Crane maintenance and rail replacement at the Potrerillos smelter Potrerillos smelter 2025
- 03 Boiler banks, wall panels and boiler maintenance Smelter and thermoelectric plant 2020 and 2021
- 04 Flash Furnace cooling system Chuquicamata smelter 2023
- 05 Replacement of casting wheels 3 and 4 Chuquicamata smelter 2021 and 2023
- 06 Flash Furnace ancillary works contract Chuquicamata smelter 2021
- 07 ZeCor-Z welding and acid plant maintenance Acid plant 2021
- 08 Fabrication and maintenance of dryer 6 coils Chuquicamata smelter 2024
- 09 Flash Furnace and boiler cooling, 18 inch line Chuquicamata smelter This sheet
- 10 Crane rail replacement at the Chuquicamata smelter Chuquicamata smelter 2021
- 11 Oxygen lines of 16, 20 and 24 inches Chuquicamata smelter 2020
- 12 Electrostatic precipitator maintenance Chuquicamata and Ministro Hales
Do you have a similar project at your plant?
Tell us the scope, the site and the schedule. We reply within one business day with a proposal.