Crane maintenance and rail replacement at the Potrerillos smelter
Maintenance of the PH cranes in the smelter building, rail replacement, and fabrication and erection of structures at the Potrerillos smelter of Codelco Salvador, with a workforce of 75.

In the Potrerillos smelter building, LTF carried out maintenance of the PH cranes that travel along the building, replaced the rails they run on, and fabricated and erected structures for the smelter. It is work at height, on the beams and platforms of the building, planned together with plant operations.
The job was carried out with a workforce of 75 and was documented in the photo and video record LTF made on site in December 2025. That record includes the testimony of Nicolás, the company’s mechanical advisor on structural erection, about the trade and the training of younger workers.
Scope delivered.
What LTF delivered on this project, item by item. The photo follows each item as you scroll.
- 01
Maintenance of the PH cranes in the smelter building
The PH cranes travel along the smelter building. Their maintenance is work at height, on beams and platforms, planned together with plant operations.
- 02
Rail replacement in the smelter building
The rails the cranes run on were replaced, working at height on the building beams.
- 03
Fabrication and erection of structures for the smelter
Structural erection had the mechanical advice of Nicolás, whose testimony about the trade is part of the project record.
- 04
Workforce of 75
The job was documented in the photo and video record LTF made on site in December 2025.
Video record.
Filmed on site. Turn on the sound to watch the full record with audio. English subtitles are shown over the original Spanish captions.
Project record.
Photos taken on site. Tap any image to see it in full, zoom in and browse all 21 from the project.
Potrerillos smelter, Atacama Region.
Site context
The Potrerillos smelter and refinery belongs to Codelco’s Salvador Division and sits in the Andean foothills of the Atacama Region. It processes concentrates from the Division itself and from other operations, and runs a Teniente converter and Peirce-Smith converters.
It is a plant under constant renewal: in July 2021 it carried out a 12-day partial shutdown, with 260 contractor workers, on the Teniente converter, the evaporative cooling tower and the wet precipitators, according to Reporte Minero. In 2026 it received a new Peirce-Smith converter shell manufactured in Chile, according to Nueva Minería.
LTF Montajes Industriales · +56 9 9431 6903 · [email protected] · ltfmontajes.cl
Boiler banks, wall panels and boiler maintenance
Codelco, Chuquicamata Division · Smelter and thermoelectric plant, Chuquicamata. Fabricated at the LTF shop View the sheet
Project index
12 project sheets for Codelco- 01 Boiler tube banks for the Chuquicamata smelter Chuquicamata smelter 2025
- 02 Crane maintenance and rail replacement at the Potrerillos smelter Potrerillos smelter This sheet
- 03 Boiler banks, wall panels and boiler maintenance Smelter and thermoelectric plant 2020 and 2021
- 04 Flash Furnace cooling system Chuquicamata smelter 2023
- 05 Replacement of casting wheels 3 and 4 Chuquicamata smelter 2021 and 2023
- 06 Flash Furnace ancillary works contract Chuquicamata smelter 2021
- 07 ZeCor-Z welding and acid plant maintenance Acid plant 2021
- 08 Fabrication and maintenance of dryer 6 coils Chuquicamata smelter 2024
- 09 Flash Furnace and boiler cooling, 18 inch line Chuquicamata smelter
- 10 Crane rail replacement at the Chuquicamata smelter Chuquicamata smelter 2021
- 11 Oxygen lines of 16, 20 and 24 inches Chuquicamata smelter 2020
- 12 Electrostatic precipitator maintenance Chuquicamata and Ministro Hales