Thirteen tonnes and many parts: a delicate lift. That is how the LTF team itself described it in the dispatch record.
At the Concón shop, boiler bank No. 6 for the boiler of the Chuquicamata smelter completed its fabrication in October 2025. At about 13 tonnes and with many parts inside, the lift called for equipment of matching characteristics: an 80-tonne crane.
The bank was loaded onto a lowboy truck and traveled under escort to the smelter, where it is installed in the boiler to replace the existing one. On site, LTF has worked with telescopic cranes and boom trucks to lift sections of oxygen lines and piping at the Chuquicamata acid plant, and in the maneuvers at the Potrerillos smelter.
Service: Mechanical worksWhat we deliver.
Every point comes from a real LTF project: each project sheet is linked below.
Matching crane
An 80-tonne crane for a bank of about 13 tonnes with many parts inside.
Loading and securing
Loading onto a lowboy truck and securing the unit before leaving the shop.
Escorted transport
Escorted trip from the shop to the smelter, where the unit is installed.
The projects behind it.
Boiler tube banks for the Chuquicamata smelter
Fabrication at the Concón shop of boiler tube banks for the convection section of the Chuquicamata smelter boiler, from the receipt and inspection of the A192 tubes to the escorted dispatch of boiler bank No. 6.
View the project sheet
Oxygen lines of 16, 20 and 24 inches
Fabrication and installation of 16, 20 and 24 inch oxygen lines for the Chuquicamata smelter, with SSPC-SP5 blasting and painting, installation of flowmeters and pneumatic testing of the system. Workforce of 50.
View the project sheet
Crane maintenance and rail replacement at the Potrerillos smelter
Maintenance of the PH cranes in the smelter building, rail replacement, and fabrication and erection of structures at the Potrerillos smelter of Codelco Salvador, with a workforce of 75.
View the project sheetFrequently asked questions.
Answers based on the published projects. For your case, write to us: we reply within one business day.
Request a proposal →How was boiler bank No. 6 dispatched?
It was lifted with an 80-tonne crane, loaded onto a lowboy truck and traveled under escort from the LTF shop in Concón to the Chuquicamata smelter.
How much does boiler bank No. 6 weigh?
About 13 tonnes, with more than 1,000 welded joints.
Does LTF carry out lifts on site?
Yes. On site it has worked with telescopic cranes to lift sections of oxygen lines and piping at the Chuquicamata acid plant, and in crane maneuvers at the Potrerillos smelter.
Services
Processes and equipment
The plant equipment and systems LTF has fabricated, installed and maintained.