Fabrication shop in Concón, Valparaíso Region.

The boiler tube banks for the Chuquicamata smelter were fabricated at the Concón shop: from the receipt of the A192 tubes to the escorted dispatch of boiler bank No. 6.

Regions and sites

From the truck carrying tubes to the lowboy truck: six to seven months of fabrication in Concón. Receipt, inspection, cutting, jig layout, welding, certification and lifting, at the same shop.

Welding in the shop booth

In July 2025 the LTF shop in Concón received two trucks carrying the complete order of A192 boiler tubes and headers, shipped from Argentina, to fabricate the banks of the convection section of the Chuquicamata smelter boiler. The quality team inspected the lot against the purchase order and the technical specifications before releasing it.

Following the fabrication drawings, each serpentine coil was cut, sized, laid out on jigs and welded until the bank was complete. Boiler bank No. 6, weighing about 13 tonnes and with more than 1,000 welded joints, was certified and, in October 2025, lifted with an 80-tonne crane onto a lowboy truck to travel under escort to the Chuquicamata smelter.

Service: Mechanical works

What we deliver.

Every point comes from a real LTF project: each project sheet is linked below.

Receipt and inspection

Unloading and storage of the material in transit, inspection of tubes and headers against the purchase order and the technical specification, and quality release before fabrication.

Fabrication to drawings

Cutting, sizing, jig layout and welding of each serpentine coil, up to banks with more than 1,000 welded joints.

Certification and dispatch

Quality certification of the finished bank, lifting with an 80-tonne crane, loading onto a lowboy truck and escorted transport to the smelter.

13t
Weight of boiler bank No. 6
+1,000
Boiler tube welded joints
80t
Capacity of the lifting crane
2
Trucks with the complete tube order

Frequently asked questions.

Answers based on the published projects. For your case, write to us: we reply within one business day.

Request a proposal →
What is fabricated at the LTF shop in Concón?

Among other work, the boiler tube banks for Codelco’s Chuquicamata smelter, fabricated in 2025 from the receipt of the A192 tubes to the dispatch of boiler bank No. 6.

How long did it take to fabricate boiler bank No. 6?

About six to seven months, including fabrication, quality certification and dispatch.

How is a 13-tonne unit dispatched?

Boiler bank No. 6 was lifted with an 80-tonne crane, loaded onto a lowboy truck and traveled under escort to the Chuquicamata smelter, where it replaces the existing bank in the boiler.

Related solutions

Services

Regions and sites

Offices, fabrication shops and smelters where LTF has carried out its projects.

All solutions
Contact

Let’s talk about your next project.

Tell us the scope, the site and the schedule. We reply within one business day with a proposal.

WhatsApp